Published specificationsOperation announced

Colt Inzai Data Centre 4

Inzai City, Chiba Prefecture

Hyperscale facility in Inzai City where Phase 1 commenced operations in February 2025.

ContactOfficial websiteChecked 2026-09-23
CapacityNot verified
Rack powerPhase 1: 4.8MW operational; approximately 20MW at completion
Cooling methodCRAH and chilled-water cooling.

Published specifications

status
operationalInzai 4 phase 1 · Operations commenced on 2025-02-26
it capacity
4.8MWoperational phase 1 · Separated from the overall planned 20MW

Differences between published sources

  • Although some parts of the official facility page still indicate it is under construction, the official opening announcement explicitly states the operational launch of Phase 1 with 4.8MW.

Notes

  • The approximately 20MW capacity at completion has not been recorded as the currently operational capacity.
  • Basis for final objective adoption: Confirmed the operational launch of Phase 1 (4.8MW) in February 2025 via Colt DCS official press release.